Wednesday, July 8, 2009

Construction is continuing on schedule except for the storm sewer installation on Overlook Drive, which is only partially completed due to a conflict with an existing gas service line. Milling on Springdale & Highland Terrace is schedule to occur on Wednesday, July 8th. Harvest and Willow will also be milled later this week. Paving (weather dependent) is planned to start on Thursday. All concrete work has been completed.